PROJECTS

COMMISSIONED SOLAR PROJECTS
Name of the Project
Capacity
(in MW)
Status
Grid connected Ground based solar project
22
Commissioned at Manmunda in Boudh District.
01
Commissioned at Mukhiguda in Kalahandi District.
02
Commissioned at New Bolangir Grid Substation in Bolangir District.
01
Commissioned at Baripada Grid Substation in Mayurbhanj District.
02
Commissioned at Jayanagar Grid Substation in Koraput District
Grid connected Rooftop Solar Project, MNRE
4
Commissioned in March 2019 on 65 Govt. buildings in
Bhubaneswar (39) & Cuttack (26) on PPP mode.
SOLAR PROJECTS UNDER PIPELINE
Name of the Project
Capacity
(in MW)
Present Status
Ground mounted Solar Project at Chipilima
10

Project will be taken up shortly.

Ground Mounted Solar PV Project at Boudh District.
54
  • Agreement to lease has been signed on 09.09.2022 in between IDCO & GEDCOL.
  • Work order has been issued to GERMI on 25.10.2024 for DPR preparation.
  • Land survey work completed.
  • Draft DPR has submitted by GERMI, which is under scrutiny

Floating Solar Project in Hirakud Reservoir
500
  • GEDCOL submitted the DPR to 4th SWC for in-principle approval in favour of GEDCOL for implementation of the project.
  • As per decision in 4th SWC, the proposal will be revised & re-submitted.
Floating Solar Project in Indravati Reservoir
160
SMALL HYDRO ELECTRIC PROJECT UNDER PIPELINE
Name of the Project
Capacity
(in MW)
Status
Kanupur Small Hydro Project, Keonjhar
3
  • The revised DPR has been prepared by GEDCOL based on design discharge of Kanpur Main Canal i.e. 35.05 Cumec.
  • The revised installed capacity is 3MW(2X1.5 MW) instead of 4.2 MW.
  • DPR has been submitted to EIC(Elecy)-cum-PCEI,Odisha and EIC(Water Resourcses), Odisha for their considered views and comments.
  • Project layout plan has been submitted to Chief Construction Engineer, Kanpur Irrigation Project for their approval.
  • After obtaining approval from cocerned authorities and completing the required procedures, the project will commence.
Jambhira Small Hydro Project, Mayurbhanj
3

Project will be taken up after getting confirmation of Water availability from Department of Water Resources as the water availability depends on construction of Ichha dam (in Jharkhand) which is in the upstream of the Jambhira dam. Construction work of Ichha Dam is under progress

Telengiri Dam Toe SHEP in Koraput District
1.2

WAPCOS has submitted the Detailed Project Report(DPR) which is under scrutiny.

Galigaddar Water fall in Kotia Panchayat of Koraput district in the state of Odisha
---

Work Order has been issued to M/s WAPCOS for preparation of Feasibility Report.

Feasibility Report for following 5 (five) nos. of SHEP
59.5

GEDCOL has been prepared Feasibility Report(FR) for following five nos. of Small Hydro Electric Project with an approximate capacity of 59.5 MW and also submitted the same to the State Nodal Agency(GRIDCO).

Sl No.
Name of the Project
District
Name of the River
(in MW)
Approximate
Capacity
(in MW)
01 Kandhamuni Sundargarh Brahamani 19
02 Bhitarajhola Rayagada Nagabali 11
03 Jiranga Gajapati Mahendra
Tanaya
4.5
04 Kussa Kandhamal Bagh 13
01 Kumbising Ganjam Bahuda 12
Total Capacity in MW
59.5
FLOATING SOLAR PROJECTS
Pre-Feasibility Report by EU Consortium
  • European Union Consortium has conducted studies on 12 hydro & irrigation reservoirs in the State and prepared PFR for approximately 5040 MW floating solar potential on 17,800 acres of water surface area in Nov. 2019
  • DPR for 2 large scale reservoirs in Hirakud and Indravati with capacity of 500 MW & 160 MW respectively has been prepared by European Union.
  • As per decision of 4th SWC, the proposal will be re-submitted after discussion with RE Nodal Agency GRIDCO, OPTCL and Water Resource Department.
PROJECTS TO BE DEVELOPED UNDER JV MODE
Name of the Project
Capacity
(in MW)
Status
Mandira Small Hydro Project, Sundargarh
to be developed under JV mode with SAIL
10
  • Contract Agreement is executed with EPC Contractor for setting up of 10 MW Mandira,SHEP
  • Survey work completed
  • Site office, Store, Staff Accomodation, labour shed completed. Installation of batching plant completed.
  • Quality control lab established.
  • Leased Deed has been signed with District Collector, Sundergarh.
  • Excavation of Approach Conduit, Penstock, Tailrace Pool and Tail Race Channel is under progress.
  • Some Major drawings and designs of the power Houses are approved by the competent authority of GSPCL.
  • The work has been commenced and the project to be commissioned by 2026-27
Floating Solar Project with NHPC,
UMREPP Scheme, MNRE
500
  • MOU executed with NHPC on 20/07/2020.
  • Project will be taken up in Joint Venture mode with NHPC.
  • The Promoters agreement, MoA and AoA has been signed on 04.01.2022 for formation of JV Company.
  • In the 1st Phase the JV Company is going to implement 300 MW Solar projects on Rengali Reservoir with MNRE approval which will start generating Solar Power within coming two years. GEDCOL has conveyed its consent to NHPC re-tendering on behalf of JV company.

  • Re-tender was floated on 05.04.2023 & BHEL was the single bidder. Price bid opened on 01.09.2023 and price negotiation is under progress.

Contact Us

Green Energy Development Corporation Of Odisha Ltd. OHPC Corporate Office, Janpath, Bhoinagar, Bhubaneswar-751022.

: 0674-2542922

: 0674-2542102

: [email protected]